By Huw Wilkins, Senior Associate, Fenwick Elliott
Indemnities are common in construction contracts, and will often be a major discussion point in contract negotiations, but they are often misunderstood. There are a number of reasons for the uncertainty around indemnities, including:
The purpose of this article is to outline what makes an indemnity different to a term of a contract and to address some of the issues that parties should consider when drafting indemnities.
An indemnity is a promise to protect someone against a loss or other financial burden. But, an indemnity is different to both a guarantee and a breach of contract.
Construction and engineering contracts commonly include indemnities from contractors to employers. The JCT and FIDIC standard forms include indemnities in respect of:
However, although previous editions of NEC contracts included indemnities, the NEC4 suite of contracts does not use the term "indemnity", in part because the term is not well understood outside the UK. NEC45 now lists the client’s liabilities in clause 80.1, and the contractor’s liabilities in clause 81.1.
The usual rules of contractual interpretation apply to indemnities (in fact, the leading case on contractual interpretation, Wood -v- Capita Insurance Limited,6 concerned the interpretation of an indemnity). The scope and application of an indemnity clause will, therefore, depend on its terms. So, when drafting and negotiating an indemnity, parties should avoid ambiguities – which can be difficult when indemnities are commonly heavily negotiated.
A party bringing a claim for a breach of contract may not be able to recover all its losses. It will only recover those losses falling within one of the two limbs set out in the case of Hadley -v- Baxendale7 being:
It is often thought that the beneficiary of an indemnity is entitled to 100% of its loss, irrespective of how remote that loss is. As is often the case, the reality is not quite so clear.
So, if contracting parties intend to exclude the rule of remoteness, they should make that clear using very clear and unambiguous wording. In the case of Capita (Banstead 2011) Limited -v- RFIB Group Limited,10 the parties referred to “liabilities costs claims demands or expenses which [it] may suffer or incur arising directly or indirectly ..." which the Court considered to include losses under both the first and second limb of Hadley -v- Baxendale.11
A party bringing a claim for a breach of contract must demonstrate that it has taken reasonable steps to mitigate its loss. Any losses that could have been avoided (or it should reasonably have avoided) will not be recoverable.
It is commonly thought that an indemnified party is not subject to the usual requirement to mitigate its loss. But, whether or not there is a requirement to mitigate will be determined in the same way as whether the rules of remoteness apply – if the indemnity is for a debt claim, there will be no requirement to mitigate. But, if the indemnity relates to a damages claim, then it will be a question of contractual interpretation.
Whether or not a contractual cap on liability will cover an indemnity is a question of contractual interpretation. So, to be sure that the cap on liability applies to indemnities (as well as claims for breach of contract), the contract should expressly state that to be the case. This can be done either in the indemnity clause or, more likely, in the clause which includes the cap on liability.
Unless there is clear wording to the contrary, an indemnified party will also be able to pursue a claim for damages (although it will not be able to recover the same loss twice, in line with the usual principle against double recovery).
It is likely that arguments around indemnities will continue between parties’ negotiating construction contracts. Employers will likely continue to include indemnities in their drafts, which contractors will look to exclude, or reduce, the impact of. There are some lessons to be learnt from the caselaw around indemnities for contractors:
June 2022