By Huw Wilkins, Senior Associate, Fenwick Elliott
Keating on Construction Contracts describes a global claim as a claim that provides "an inadequate explanation of the causal nexus between the breaches of contract or relevant events/matters relied upon and the alleged loss and damage or delay that relief is claimed for".1
The SCL's Delay and Disruption Protocol (2nd edition) provides an alternative definition of a global claim, being "one in which the contractor seeks compensation for a group of Employer Risk Events [i.e. something which under the contract is at the risk and responsibility of the Employer] but does not or cannot demonstrate a direct link between the loss incurred and the Individual Employer Risk Events."
Those opposed to global claims argue that they contravene the generally accepted legal position that a party must prove a causal link between the sums it claims and individual events (in the context of contractors’ claims being either events under the contract entitling the contractor to loss and expense, or breaches of contract entitling the contractor to claim damages). This is why, historically, the courts have not looked favourably on global claims. In Wharf Properties -v- Eric Cumine Associates (No.2),2 faced with a global claim, Lord Oliver described the pleading as "hopelessly embarrassing" and referred to the claimant's obligation "to alert the opposite party to the case which is going to be made against him at trial".
However, more recently, the courts have taken a more lenient approach when considering global claims. By way of example, in the case of Walter Lilly & Co Ltd v DMW Developments Ltd,3 although Mr Justice Akenhead concluded that the claim before him was not a global claim, he did consider (obiter) that “in principle, unless the contract dictates that a global cost claim is not permissible if certain hurdles are not overcome, such a claim may be permissible on the facts and subject to proof."
Mr Justice Akenhead also set out the following requirements with regards to global claims:
A contractor may seek to advance a global claim if it is impractical or impossible to demonstrate causal links between specific events and losses such that a global claim is the only way for the contractor to advance its claim.
Whilst a global claim may, on its face, be relatively quick and inexpensive to formulate, a contractor will need to meet the requirements set out by Mr Justice Akenhead in the Walter Lilly case. Contractors should also note the comments of Mrs Justice Carr in the more recent case of John Sisk & Son Ltd v Carmel Building Services4, that for a party endeavouring to prove a global or total costs claim, “[t]here are added evidential difficulties in proving a global or total costs claim.”
Although the Court’s approach to global claims appears to have softened in recent times, it will be easier for an employer to undermine a global cost claim. This means that, whilst it might be quicker and less expensive for a contractor to put forward a global claim, a contractor will be far better placed if it can present an itemised claim, demonstrating causal links between its losses and the employer's actions (or issues that are at the employer's risk).
May 2022