On 29 August 2013, the Technology and Construction Court handed down judgment in Parkwood Leisure Limited v Laing O’Rourke Wales & West Limited [2013] EWHC 2665, and considered for the first time whether a collateral warranty is a construction contract for the purposes of Part II of the Housing Grants, Construction and Regeneration Act 1996 (the “Act”).
To the surprise of the construction industry (and its lawyers), the court confirmed that, depending on their precise wording and the circumstances, collateral warranties could be regarded as being construction contracts under the Act, in which case the beneficiary would be rendered eligible for statutory adjudication.
This twenty-eighth issue of Insight considers the ramifications of the decision for the construction industry, and also provides practical tips for those who do not wish their warranties to be subject to statutory adjudication.
Laing O’Rourke Wales & West Limited (“LOR”) entered into a standard JCT Design and Build contract (the “Contract”) in respect of a leisure facility in Cardiff. Before the works completed, LOR entered into a deed of warranty with the funder, first purchaser and mortgagee as required by Article 10 of the Contract, naming the tenant, Parkwood, as beneficiary.
The warranty provided:
“1 The Contractor warrants, acknowledges and undertakes that:-
1 it has carried out and shall carry out and complete the Works in accordance with the Contract;
2 … it owes a duty of care to the Beneficiary in the carrying out of its duties and responsibilities in respect of the Works;
3 it has exercised and will continue to exercise all reasonable skill and care [in respect of the design] …
…
7 it has complied and will continue to … carry out its obligations under the Contract [including in terms of proceeding regularly and diligently].”
Following completion of the works almost a year later, LOR had failed to complete remedial works that Parkwood alleged it was contractually bound to undertake and Parkwood therefore sought to enforce the terms of the warranty. Parkwood wished to adjudicate its dispute with LOR and it therefore sought a declaration from the court that it was entitled to bring statutory adjudication proceedings against LOR on the basis that the warranty was a contract for construction operations caught by the Act.
In light of the wording of the warranty, the Judge held that it was a construction contract for the carrying out of construction operations under the Act, even though it had been given retrospectively.
The recital confirmed that the Contract was for the design, carrying out and completion of the construction of a swimming pool development, and clause 1 of the warranty contained an obligation upon LOR to complete and carry out the works in accordance with the Contract with reasonable care and skill.
The key point about the warranty which swayed the Judge was the fact that it related in part to the execution and completion of works that were not yet complete, albeit LOR had already completed a significant proportion of the works and design. LOR’s warranties were not therefore limited to a past state of affairs but, rather, they constituted a positive obligation upon LOR to carry out and complete future works to the standard, quality and state of completeness required by the Contract.
The Judge, however, made it clear that it does not automatically follow that all warranties will be regarded as being construction contracts under the Act: everything depends on the precise wording of the warranty and the surrounding background facts.
This decision is important because it challenges the 15-year status quo that warranties are not caught by the Act and are therefore not capable of being adjudicated. If the decision stands, there will be a number of ramifications for the construction industry.
Those who provide warranties may face new adjudication claims by beneficiaries and contractors, subcontractors and consultants that had not previously been considered to be possible.
The decision will no doubt be welcomed by beneficiaries of warranties as adjudication may be seen as a more expeditious and cost effective way to enforce the terms of a warranty than via court or arbitral proceedings.
There will undoubtedly be an increase in jurisdictional challenges as parties will seek to establish as a preliminary point whether the warranty in question is a contract for construction operations, and is therefore capable of being adjudicated. Unless the parties agree to be bound by the adjudicator’s decision as to whether the warranty is caught by the Act (which would be very unlikely as the issue is a brand new one), they will be left with a non-binding decision which may result in one or both parties refusing to participate in the adjudication any further, or a challenge on jurisdiction at a later date.
When preparing new warranties, consider the drafting of your warranty very carefully if you do not wish it to become subject to statutory adjudication. You should:
The wording of the warranty is important, but the timing of its execution is even more important. In Parkwood, the Judge suggested that any warranty given prior to practical completion should be treated as being a contract to carry out future works, as opposed to a warranty in respect of works that have already been carried out. If practical (and often it is not) you should therefore avoid executing a warranty until practical completion has been achieved as you will then only be warranting a state of affairs in respect of works that have already been carried out.
This is the first judicial authority as to whether warranties should be regarded as being construction contracts for the purposes of the Act. The Act itself is of very little use as it only provides an illustration of what an agreement for the carrying out of construction contracts might include (and exclude). Notably, it does not say that warranties are not covered by the Act.
The Judge emphasised that there can be no doubt that the reference to a “contract” must mean a contract under English law. But what is difficult to reconcile about the decision is how a warranty can be regarded as being a construction contract (or at the very least a contract in the usual sense of the word) in circumstances where the beneficiary is not also the employer under the underlying contract; where the beneficiary would be unlikely to be able to exercise any control over the conduct of the works; and where consideration is not usually provided by the beneficiary of the warranty.
“If the decision stands, there will be a number of ramifications for the construction industry.”
At the time of writing, it is not yet known whether the decision will be appealed to the Court of Appeal and so for the time being the decision stands, until and unless the Court of Appeal takes a different view.